Pipeline · Interconnection Queued

Genesis Wind

75 MW utility-scale wind project on the site of a decommissioned wind farm in Logan County, Colorado. ~7,600 acres under wind lease, setback, and good-neighbor agreements with 21 landowners.

Logan County, CO Public Service Company of Colorado WECC Target COD 2029-Q4
Wind MW-AC
75
Status as of
May 7, 2026

Site

About 7,600 acres in Logan County, Colorado, under wind lease, setback, and good-neighbor agreements with 21 landowners. Re-development of a prior decommissioned wind farm, with existing access roads, prior resource studies, and demonstrated landowner support.

Interconnection

Peetz 115 kV Substation on the Public Service Company of Colorado (PSCo) system. 2025 DISIS submitted; scoping cleared with no major issues. Provisional study path could complete by end of 2027.

Status